COUNCIL WORKS ON WILLIAM BERRY DRIVE FROM MID-MAY 2026

The council will be commencing the final leg of William Berry Drive upgrades from Mid-May 2026. This stage of works completes an upgrade that will improve safety and traffic flow for motorists, pedestrians and cyclists.

This final stage includes stormwater renewal and road resurfacing works on the eastern side of William Berry Drive behind Morayfield Shopping Centre and adjacent to the train line.  Construction will be sequenced to minimise impact with three stages to occur as follows:

 

Stage 1 – Mid May to early July (approximately 7 weeks) – see Red on map

Stage 2 – Early July to early August (approximately 4 weeks) – see yellow on map

Stage 3 – Early August to Mid September (approximately 6 weeks) –  see green on map

 

Please note that the above timings are subject to weather.  Works will generally be undertaken during 6am to 5pm Monday to Friday. As sections of the road will be closed as per the map during these times, we ask that you seek alternative routes when travelling around the Shopping Centre.

 

Should you require any further information, please contact councils team on 3205 0555 or [email protected]

You might also like

BIG W CLICK AND COLLECT – CHANGES TO ACCESS

Please note that from Mid May there will be council roadworks occuring on William Berry Drive …

Roadworks – Update from Council

Council have notified us that the next stage of road works around the Centre will be …

Coffee, Cops & Conversation – 2026 Dates

Coffee with a Cop provides a forum for police officers and the community to come together …